Site development works to realize this masterplan included minimal leveling of the ridges to make platforms just large enough to accommodate the buildings, and construction of the tunnel and shaft, access roads and a series of seven bridges.
Construction of Lab 1 and the Center Building on one of the site ridges commenced in March 2008 and was completed in March 2010.
Lab2
Construction of Lab 2 on an adjacent ridge commenced in November 2010, and is due to be completed in Spring 2012.

The new Lab 2 building will be linked to the existing facilities by a covered skywalk across the ravine between them.
Auditorium
A 500-seat auditorium is also presently under construction at the entrance to the campus, and is due to be completed in February 2012.